NRD PROJECTS
Soil erosion, flooding and
surface/groundwater drainage are all challenges that are faced in this District.
Our goal is to use each acre within its capability and to treat each acre
according to its needs as set forth in the technical guidelines adopted by the
District. The District has included the Erosion and Sediment Act, adopted by the
Nebraska Legislature in 1986, as part of the NRD's Master Plan. The Act
established a state-wide program designed to reduce erosion to tolerable levels
throughout the state. Cost-share programs are available to encourage
conservation measures on privately owned land that will produce long-term
benefits for the general public; flood prevention, flood control and channel
rectification fall under this budget category.
Current Projects: (click
links for information in pdf)
*Prairie/Silver/Moores
Flood Control Project Click here
(See description under 3. below)
Upate:
On Sept. 3, 2009, Milt
Moravek, assistant manager, reported on the bid letting of the construction of
cells for the Prairie/Silver/Moores Flood Control Project. Ten bids were
received. The lowest bid by Hooker
Brothers Construction Company, Grand Island, was awarded with a bid at
$1,720,914.On July 23, 2009, Milt
Moravek, assistant manager, reported that there are currently two contractors
working on the project. Moravek said
that construction of box culverts have been moved up to the current Phase of
construction to help with flood control in the areas east of the Ordinance
Plant, including the northern area of Grand Island.
A total of 2.6 million cubic yards of dirt will be moved as part of
construction. The board of directors
will tour the project, as well as other NRD projects, this fall.
*Proposed Elm
Creek Watershed
Click
Here
Upate: On May 28, 2009,
The
board approved the following action on the proposed Elm Creek Flood Control
Project:
1)
Ron Bishop to work with Jerry Kenny, executive director of the Platte River
Recovery Implementation Program, on a Memorandum of Understanding that would
detail financing on studies to be conducted for the proposed Elm Creek
FCP. On Sept. 3, 2009 (August Board Meeting)
2)
Expansion of study with Olsson Associates to determine delivery canal capacity,
discharge capacity, groundwater impacts and sizing options for water storage.
*Proposed
Central City/Marquette Hike and Bike Trail
Click Here
Update: 9/24/09-
Milt Moravek, assistant manager,
reported that the Upper Big Blue NRD voted in support of joining the Central
City-Marquette Joint Action Agency. Ladd
Reeves was appointed to sit on the committee for the Joint Action Agency to help
outline the proposed trail. Ed Kyes
will serve as alternate.
1. Wood River Flood Control Project
Click here for DNR Story on the WR Flood Control Project The Flood of 2005 Details
When completed, this project will carry excess water from the Wood River and Warm Slough into the Platte River to alleviate flood damage to area landowners and businesses. The cost estimate for the project is over $17 million. CPNRD provided 42.5 % of the local sponsor share of the study, completed by the Corps of Engineers. The City of Grand Island provided 35% and Hall and Merrick Counties each provided 11.25%. Sixty percent of the non-federal share will be paid for by the State Resources Development Fund. Click here for photos of the 2005 Flood.
In June 2008, the City of Grand Island
received over 7 inches of rain during the first week of the month. This
created substantial problems for landowners and homeowners in the area; however,
it brought great appreciation for the Wood River Flood Control Project.
Without the completion of this project, a number of homes would've been
devastated. Below is an article in the June 11th edition of the Grand
Island Independent:
The Grand Island Independent Posted Jun 10,
2008 @ 11:59 PM
Park Water to be Dumped into Diversion Channel by Tracy Overstreet
2. Kearney Northeast
The newly developed areas in the city of Kearney will no longer have to worry
about flooding with the completion of the Kearney Northeast Flood Control
Project. The project was started in 1990 to alleviate increased flooding from
storm runoff on a tributary of the Wood River. In
1995, Miller & Associates developed a plan to stop a serious erosion problem
and flooding in the northeastern part of Kearney. The project includes channel
improvements, drop structures, road crossings and a detention cell. The City of
Kearney, Buffalo County and the NRD agreed to split the costs of the project and
to do the construction in phases so taxpayers wouldn’t have a large one-time
impact. The project was completed in
three Phases. Phase I and III widened the existing channel of the Wood River,
starting at the drop structure and meanders west and south to a point near 56th
Street on Eaton Road. The detention cells are located approximately 1/2 mile
north of ‘N’ Avenue and 56th Street. Construction included 300,000 yards of
excavation with a 50 acre/feet storage design for a 100 year storm and a 50
acre/feet storage design for a 25-year storm. Approximately 75,000 yards of soil
was excavated to create a new channel for the project. Phase
II, which primarily consisted of channel improvements, was the last Phase to be
constructed. Improvements were made from the Phase I channel south to 39th
Street then west to Antelope Road; and from 56th Steet to Avenue N.

3. Upper Prairie/Silver/Moores Flood Control Project- Click here for project information in PDF.
UPDATE
11/20/2008 In June of 1967 what was estimated
as a 75 year storm event occurred in Grand Island causing severe flooding and
inundating 42 square miles in northern and western Grand Island.
Total property damage in Grand Island was estimated at $3,250,000.
More Recently on May 11, 2005, portions of Hall County
received in excess of 7 inches of rainfall within a period of 24 hours causing
an estimated $12 to $15 million in damages in Hall County, and damages to an
estimated 2,769 homes and businesses.
Project Background
In June of 1967 what was estimated
as a 75 year storm event occurred in Grand Island causing severe flooding and
inundating 42 square miles in northern and western Grand Island.
Total property damage in Grand Island was estimated at $3,250,000.
More Recently on May 11, 2005, portions of Hall County
received in excess of 7 inches of rainfall within a period of 24 hours causing
an estimated $12 to $15 million in damages in Hall County, and damages to an
estimated 2,769 homes and businesses.
In May of 2000, the Central Platte NRD and the City of Grand Island hired Parsons Water and Infrastructure to perform a detailed hydrologic analysis of the Northern and western Grand Island. The analysis was also to evaluate options for reducing flood damages to present the preferred alternative.
JEO Consulting Group, Inc. was selected in September of 2005 to provide engineering services for the design and oversight of the flood control project. The flood control project is designed in three phases. Construction of Phase 1 began in January of 2007. Completion of all three phases is anticipated in 2015.

Project Goal
The primary goal of the Upper Prairie/Silver/Moores Creek
Flood Control Project is to provide flood protection from the 100-year storm to
urban residential and commercial properties in western and northern Grand
Island. Secondary purposes of the project are to provide flood
protection to crop land and rural residents, reduction of road and bridge
damages, reduction of the rural 100-year floodplain aerial extent, removal of
western and northern Grand Island from the FEMA, and to provide wildlife
habitat. Construction is estimated
at $16.2 million for the entire project. An
estimated 2,750 homes and business, with an average flood insurance rate of $400
per year, will receive benefits from this project once completed. Success of this project is reliant on coordination with
several government agencies including; FWS, USACE, DNR, County, City and the
CPNRD. The Natural Resources
Commission is funding 52.5% of the project cost, the remaining 47.5% is funded
by the CPNRD, the city of Grand Island, Hall and Merrick Counties.
Phase 1 – Silver Creek Low Land Stormwater Detention Cells
The
first phase of the project is the construction of 4 large floodwater detention
cells along the Silver Creek channel with a total excavation near 4.5 million
cubic yards of earth. Van Kirk
Brothers Contracting located in Sutton Nebraska was awarded the contract for the
construction of the first two cells. The
cell design also includes the lowering and re-grading of Silver Creek for more
then two miles. The detention cells
will detain stormwater runoff in excess of the 2-year storm.
A 3’ x 3’ concrete box culvert will be used as the outlet and will
release the water from the cells at a rate equal to the 2-year storm.
A second 3’ x 6’ gated box culvert will be used for rapid draw down
of the cells. A berm is being placed
around the cells, approximately 2 foot above existing ground, to provide
sufficient capacity to detain runoff from the 100-year storm with a 1-foot
freeboard.
Phase 2 and Phase 3
A series of upland detention dams and an overflow channel from Prairie Creek to Silver Creek. The exact locations of the detention sites will be finalized in the final design phase of this project. Several sites are available and will be evaluated after geological investigations have been completed. The Channel between Prairie and Silver Creek will serve to carry excess flows from Prairie Creek to Silver Creek.
4. Lower Warm Slough Prairie
Updated 6/10/2008
Recent floodwaters from the Warm Slough/Trouble Creek
Watershed have been estimated to meet and probably exceed a 100-year event.
The diversion project, completed in 1993, “handled the water just
fine,” said Milt Moravek, assistant manager of Central Platte Natural
Resources District. In total, the
area of Central City received over six inches of rainfall from June 1-June 8 in
addition to all of the previous rains. While
surveying the project on June 9, Moravek said the flood control channel was
completely full and expects it to stay full for several days.
Prior to the project, there
was a history of flood damage to agricultural and urban property within Central
City; caused mainly by storm water runoff into the Warm Slough, Dry Run and
Trouble creeks. In 1967, a flood inundated much of the town.
Since the channel was dug, even before it was totally completed, the
project has prevented flood damage for the community in 1992 and two other major
rain events in 2005 and 2008.
The
Natural Resources Development Fund, Central Platte NRD, Merrick and Hall
counties, and the cities of Grand Island and Central City funded the project.
In 2002, the NRD performed snagging and clearing of the Lower Warm Slough
from Grand Island to Central City at a cost of $110,000; which improved drainage
for the entire watershed.

5. Prairie Creek Clearing
Although the Prairie Creek Flood Control
Project had a local effect, damages could be reduced on Prairie Creek by keeping
the channel clear. Projects have been completed from the mouth of Prairie Creek
in Merrick County to the Hall-Buffalo county line. Annual maintenance cost is
$10,000.
6. Prairie Slough
St. Libory residents asked CPNRD for assistance to
alleviate flood damage caused by a high water table and poor drainage from the
Prairie Slough. Howard and Merrick County boards have agreed to work with CPNRD
to develop a study to determine what options are available for the area.
Currently, proposals are being sought to plan a project that can be completed in phases.
Some work has been completed east of St. Libory.
7. Moores Creek
Project sponsors of the feasibility study for the flood control on Moores Creek include CPNRD, the City of Grand Island, Merrick County and Hall County. The commission approved the Moores Creek Project and agreed to cost-share at 65% rate. The three-phase project consisted of channel improvements, construction of three detention/retention and wildlife habitat enhancement cells, and construction of waterways and bridges to enable storm runoff. Annual maintenance cost is estimated at $20,000.
8. Lower Spring Creek
In response to landowners requests,
construction of the snagging and clearing project in Dawson County was completed
in 1995. Annual maintenance is done as needed.
9. Gibbon Spur
The project, located south and southwest of Shelton,
is designed to divert flood water drainage under the Union Pacific Railroad's
Gibbon Spur overpass on Interstate 80. The project is currently on hold due to
land rights issue, however, CPNRD continues to work with Union Pacific and local
landowners to determine if a project can still be developed.
10. Wood River Watershed
Snagging and clearing has been completed from
the mouth of the stream to Gibbon. Annual maintenance for the Wood River
Clearing Project is estimated at $10,000.
11. Dry Creek Clearing
A request from landowners to clear a channel
northeast of Cairo was prompted by debris from a windstorm or tornado. The
project was completed in 1998, however, area landowners petitioned the NRD to
clear an additional 21,000 feet. That project will be completed this winter.
Maintenance is done by the NRD.
12. Kearney West Clearing
Landowners west of Kearney, along Turkey
Creek, requested a clearing project of 2 2 miles to assist them with flooding
problems. An additional mile will be cleared and snagged in 2000. Project
maintenance is done by CPNRD.
13. Kearney West Drainage
In 1999, landowners complained in a
petition to the CPNRD Board of high groundwater levels, causing poor surface
drainage to occur on the north channel of the Platte River, which includes the
community of Odessa. The Board will consider authorization of a study to address
what possible remedies there are for the situation. All aerial photography and
mapping has been completed.
14. Kearney East Drainage
In 1998, CPNRD received a petition from
landowners about high groundwater levels due to poor surface drainage north of
I-80, between Hwy 10 & the Windmill State Recreation
Area, south of Gibbon. Due to the lack of continued landowner support, the
study to remedy this situation was not authorized.
15. Silver Creek Watershed-
This four-phase project has been completed
since 1987. The project provides flood relief in Merrick County, and encompasses
90,000 acres. Annual maintenance costs to the NRD are approximately $20,000.
16. Clear Creek Watershed
Located in Polk County, this watershed
encompasses nearly 75,700 acres and had a long history of flooding, with 15 flood control structures
completed. Cost-share from the Natural
Resources Development Fund was received on 5 of the larger structures and
Polk County provided cost-share funds for additional smaller structures.
Construction of smaller structures are performed as needed.
17. County Road Structures
The District has established a county road
structure program to help counties provide minor flood control. CPNRD has
completed a number of these structures in cooperation with the county highway
departments in several counties.
| HOME | ||||
| Contact the Site Administrator If You Notice Any Problems | ||||